Project management tank maintenance

A 96.5-metre crude oil tank in the Caspian region required repair. Repair included replacement of the annular plate, the ring seal system and complete internal re-coat and commissioning activities. Our project team successfully managed the quality and construction process.

The main activities in the project were;

  1. Soil, tank roof and wall integrity verification.
  2. Scope Challenge on inspection reports
  3. Wall and EFR structure evaluation for sealing system
  4. Design of repair method.