Catalyst switch
During a so-called turnaround, in which the production process is shut down at a refinery, we carried out catalyst activities. Together with Mourik International (main contractor), we discharged, cleaned, filled and checked 3 Tubular reactors. This work was carried out safely and on time, within 18 days. As a result, the shutdown for the customer was as short as possible. It involved 3 reactors with 4500 Tubes each, which are filled with catalyst. The work was carried out in a 24-hour work schedule. Compliments to our staff for the good execution!