Catalyst change
During a so-called turnaround, in which the production process is shut down at a refinery, we carried out catalyst activities. Together with Mourik International (main contractor), we unloaded, cleaned, filled and checked 3 Tubular reactors. These activities were carried out safely and on time, within 18 days. The shutdown for the customer was therefore as short as possible. It involved 3 reactors with 4500 Tubes each, which were filled with catalyst. The activities were carried out in a 24-hour work schedule. Compliments to our employees for the good execution!